Construction To Begin On Gage Boulevard & Reata Road Roundabout (Photo)
- 02/26/26
The City of Richland is providing advance notice of upcoming construction associated with a new roundabout at the intersection of Reata Road and the future Gage Boulevard extension.
The roundabout is being constructed by the developer of Badger Mountain South and will provide a new intersection connection for the Gage Boulevard extension while creating an additional access point to the South Orchard community currently under development. The project is designed to improve traffic circulation, safety, and long-term connectivity in the area.
Project Scope
Construction activities will include:
- Roundabout construction
- Installation of sidewalks and ADA-compliant crossings along the north side of the roundabout
- Widening of Reata Road, tapering back to existing roadway east of the project limits
- Installation of City water and storm utilities
- Relocation of a Benton County Irrigation District (BMID) water main
- New streetlights
- New asphalt paving
- New striping and signage
Construction Timeline & Traffic Impacts
Construction is anticipated to begin late February to early March 2026, with initial work occurring outside of the existing roadway.
In mid-to-late April 2026, construction is expected to shift into the roadway. At that time:
- A full road closure will be implemented on Reata Road between Southgate Way and Badger View Drive
- A signed detour will route traffic via Sagebrush Road to Bermuda Road, south of the project area
The contractor will coordinate directly with residents within the work zone to maintain access to homes and properties during detour operations. Access to the South Orchard neighborhood via Southgate Way will remain open during detour operations.
Construction is anticipated to be completed in June 2026, weather and site conditions permitting.
The City appreciates the public’s patience during construction and will continue to share updates as the project progresses.
For additional information or future project updates, visit richlandwa.gov/GageReataRoundabout.
Construction To Begin On Gage Boulevard & Reata Road Roundabout (Photo)
- 02/26/26
The City of Richland is providing advance notice of upcoming construction associated with a new roundabout at the intersection of Reata Road and the future Gage Boulevard extension.
The roundabout is being constructed by the developer of Badger Mountain South and will provide a new intersection connection for the Gage Boulevard extension while creating an additional access point to the South Orchard community currently under development. The project is designed to improve traffic circulation, safety, and long-term connectivity in the area.
Project Scope
Construction activities will include:
- Roundabout construction
- Installation of sidewalks and ADA-compliant crossings along the north side of the roundabout
- Widening of Reata Road, tapering back to existing roadway east of the project limits
- Installation of City water and storm utilities
- Relocation of a Benton County Irrigation District (BMID) water main
- New streetlights
- New asphalt paving
- New striping and signage
Construction Timeline & Traffic Impacts
Construction is anticipated to begin late February to early March 2026, with initial work occurring outside of the existing roadway.
In mid-to-late April 2026, construction is expected to shift into the roadway. At that time:
- A full road closure will be implemented on Reata Road between Southgate Way and Badger View Drive
- A signed detour will route traffic via Sagebrush Road to Bermuda Road, south of the project area
The contractor will coordinate directly with residents within the work zone to maintain access to homes and properties during detour operations. Access to the South Orchard neighborhood via Southgate Way will remain open during detour operations.
Construction is anticipated to be completed in June 2026, weather and site conditions permitting.
The City appreciates the public’s patience during construction and will continue to share updates as the project progresses.
For additional information or future project updates, visit richlandwa.gov/GageReataRoundabout.